Info Fwo

Best quality vitrified clay channels, bedded in cement mortar half-section straight main channel 100mm diameter x 300mm Half-section 90 degrees channel bend 100mm nr 0.30 4.50 6.25 1.61 12.36 150mm nr 0.40 6.00 9.38 2.31 17.69 Three-quarter section 90 channel bend 100mm nr 1.20 18.00 13.08 4.66 35.74 150mm nr 1.30 19.50 23.27 6.42 49.19 Excavate trench 225mm wide by hand, remove excavated material, average depth Excavate trench 300mm wide by hand, remove excavated material, average depth...

Grassed areas 1

Sweep up leaves with motorised vacuum cleaner 100m2 0.84 - 0.13 0.97 Treated softwood tree stakes driven into the ground Cleft chestnut tree stakes driven into the ground 200mm diameter x 1000mm high 200mm diameter x 1200mm high 250mm diameter x 1400mm high 250mm diameter x 1800mm high 600mm high 750mm high 900mm high 1200mm high

Info Fot

Earthwork support not exceeding 2m between opposite faces, depth depth not exceeding 1m Earthwork support not exceeding 2m between opposite faces, depth depth not exceeding 2m Earthwork support not exceeding 2m between opposite faces, depth depth not exceeding 4m Load surplus excavated material into barrows, wheel and deposit in temporary spoil heaps, average distance Load surplus excavated material into barrows, wheel and spread over site, average distance Load surplus excavated material into...

General Construction Data 1

1 centimetre cm 1 decimetre dm 1 metre m 1 kilometre km 100 sq millimetres 100 sq centimetres 100 sq decimetres 1000 sq metres 10 millimetres mm 10 centimetres cm 10 decimetres dm 1000 metres m 1 sq centimetre 1 sq decimetre 1 sq metre 1 hectare 1 cubic centimetre cm3 10 millilitres ml 10 centilitres cl 10 decilitres dl 1 centigram cg 1 decigram dg 1 gram g 1 decagram dag 1 hectogram hg 10 milligrams mg 10 centigrams mcg 10 decigrams dg 10 grams g 10 decagrams dag Conversion equivalents...

Kerbs And Edgings

Excavate trench, lay concrete foundation for precast concrete straight kerb, size Excavate trench, lay concrete foundation for precast concrete curved kerb, size Excavate trench, lay concrete foundation for precast concrete straight channel, size Excavate trench, lay concrete foundation for precast concrete curved channel, size Excavate trench, lay concrete foundation for precast concrete straight edging, size

Plant Names

English Latin plant names Latin English plant names

Precast Concrete

Precast concrete copings twice weatherted and twice throated, size 75 x 150 x 900mm nr 0.30 4.50 7.12 1.74 13.36 75 x 300 x 900mm nr 0.40 6.00 8.71 2.21 16.92 Precast concrete pier caps, four times weathered, size 300 x 300 x 75mm nr 1.00 15.00 7.04 3.31 25.35 450 x 450 x 75mm nr 1.20 18.00 9.90 4.19 32.09 Excavate trench by hand for kerb foundation Excavate curved trench by hand for kerb foundation Site-mixed concrete in foundation for kerb size Precast concrete kerbs, channels and edgings,...

Unit Rates

Common bricks basic price 140 per thousand in cement mortar 1 3 , stretcher bond

Hedging contd 1

Bare Root Trees

The following descriptions refer to dimensions and sizes of trees as as set out below. Whips 125 to 175cm high Feathered 175 to 250cm high Light standard 6 to 8cm girth Standard 8 to 10cm girth Selected standard 10 to 12cm girth Heavy standard 12 to 14cm girth Extra heavy standard 14 to 16cm girth Excavate tree pit, fork bottom, plant tree, backfill with excavated material including organic manure 30 of soil by volume , water and surround with peat heavy standard nr extra heavy standard nr...

Brickwork And Blockwork

Bricks per m2 brick size nr 215 x 103.5 x 65mm One brick wall English bond Flemish bond Blocks per m2 block size 414 x 215mm One and a half brick wall Two brick wall

Info Rzl

Cut down hedge, grub up roots and remove Excavate topsoil or turf and lay aside for re-use Excavate to reduce levels depth not exceeding Hours Mat'ls O amp P Total Load surplus excavated material into lorries and cart away to tip Surplus excavated material deposited and compacted in layers

Info Ofh

Excavate trench 300mm wide for 75mm clay field drain pipe and backfill with gravel trench depth, 500mm trench depth, 750mm trench depth, 1000mm Excavate trench 225mm wide for 100mm clay field drain pipe and backfill with gravel trench depth, 500mm trench depth, 750mm trench depth, 1000mm Excavate trench 300mm wide for 100mm clay field drain pipe and backfill with gravel trench depth, 500mm trench depth, 750mm trench depth, 1000mm Excavate trench 225mm wide for 100mm clay field drain pipe and...

Debtor days

This is calculated by dividing your trade debtors by annual sales and multiplying by 365. This shows the number of days' credit being afforded to your customers and should be compared both with your normal trade terms and the previous month's figures. Normal procedures should involve the preparation of a monthly-aged list of debtors showing the name of the customer, the value and to which month it relates. The oldest and largest debtors can be seen at a glance for immediate consideration of...

Estimating Costs Guide To

SMALL GROUNDWORKS, LANDSCAPING AND GARDENING Spon's Estimating Costs Guide to Small Groundworks, Landscaping and Gardening Spon's Architects' and Builders' Price Book 2008 edition Hb 978-0-415-42448-6 Spon's External Works and Landscape Price Book 2008 edition Hb 978-0-415-42444-8 Spon's Estimating Costs Guide to Finishings painting and decorating, plastering and tiling 2007 edition Spon's Estimating Costs Guide to Plumbing amp Heating 2006 edition Pb 978-0-415-38618-0 Spon's Estimating Costs...

Info Bkr

Concrete mixers up to 5.00 1.00